On February 28th, mountains, south of fuling began rumbling, like all heart, wake up the sleeping already a long time. Local villagers said: "China petrochemical in the shale gas exploration, it is said that the gas is economical and practical, we also come in handy later."
Guns from deployment of exploration in the southern branch, at present, in view of the focal region of rockfill dam with the largest domestic shale gas, 600 square kilometres of high precision 3 d seismic project.
South exploration deployment of focal page 1 hf white diamond at the end of 2012 was high yield shale gas well, the group company attaches great importance to shale gas exploration in this area, have deployed focal page 2 hf hf and 3, 4 hf well three horizontal Wells and the 3 d seismic data acquisition project.
This fine 3 d seismic exploration is the purpose of the evaluation of focal region of rockfill layer dragon stream group of shale gas generation anddistribution as well as the purpose, to carry out the "dessert" development zone, to focus on page 2 hf hf and 3, 4 hf well horizontal section of the accurate positioning and overall and efficient development of shale gas coke dam area to obtain accurate information.
According to the construction, exploration of southern hammered out the details of the time nodes: on January 14, to carry out the gun, construction lofting, who bear on February 28, seismic acquisition officially starts, before June 5, 600 square kilometres of 3 d seismic data acquisition task is complete, then work for seismic data processing and interpretation shall.
On January 14, undertake the construction task of southwest petroleum geophysical prospecting brigade 2 and 5 geophysical exploration of the two giants of the more than 200 management personnel and technical personnel, more than 4500 construction thousands of elite force of exploration equipment (sets), enter the focal shale gas of rockfill dam for trial production. During the Spring Festival, in addition to the year and the first rest day, have been drilling more than 300 sets of air drilling. To improve the quality of collected data, both parties jointly organized across fuling city, the Yangtze river and wujiang river waters, such as a factory that influences the quality of seismic earthquake research experiment was carried out. In order to catch time, grab the progress, to undertake the project focal dam 3 d seismic data acquisition processing tasks sinopec geophysical institute specialized processing equipment from the northeast attune, organize technical personnel to the fifth day arrive to fuling construction site, online, test work.
Around the construction exploration target adjustment plan, reasonably adjust the construction sequence, starting from the middle construction, place the most urgent in the head, brings to the construction of a certain pressure. Contractor 2, wuwu said, will be before the April 20, the most urgent focus on page 2 hf hf and 3, 4 hf well around 2 km of seismic data completely out, working for another round of drilling and provide solid precise seismic data, achieve exploration.
Party a and party b has also taken to choose the appropriate measures of mom points away from crops and houses to ensure no losses to local farmers.